Categories
Intel

Fatwa Summary: MJLA Fatwa 242799712 (Confiscation of Performance Bond after Execution at Contractor’s Expense)

The Ministry of Justice and Legal Affairs held that the confiscation of a performance bond is a contractual penalty that may only be imposed where a law, regulation, or the contract expressly provides for it. Neither the Tender Law nor the 1999 Standard Contract for the Construction of Buildings and Civil Works permits a government entity to confiscate a contractor's performance bond when it withdraws the works and executes them at the contractor's expense. Once the entity has recovered its price differences, delay fines, and expenses from the contractor, the 1999 Standard Contract requires it to return the bond.


You do not have a valid subscription to view Decree Intel. Decree Intel is a database of Omani legal research material that covers explanatory notes, government entity overviews, and case and fatwa summaries. Decree Intel is a separate subscription from Decree Legislation. Contact us to learn more.

Categories
Intel

Case Summary: Supreme Court (Commercial Circuit) Contestation 136/2005 (Waiver of Arbitration Clause by Denial of Contract)

The Supreme Court held that an arbitration clause is not a matter of public order and may be waived expressly or impliedly, but whether a party has in fact waived it is a question of fact for the trial court. A letter in which a party denies being bound by any agreement with the other side, and on that basis declines a proposal to arbitrate, does not amount to a waiver of the arbitration clause in that agreement.


You do not have a valid subscription to view Decree Intel. Decree Intel is a database of Omani legal research material that covers explanatory notes, government entity overviews, and case and fatwa summaries. Decree Intel is a separate subscription from Decree Legislation. Contact us to learn more.